Dewatering NOC

Introduction

To ensure that contractors who dewater on site do so in a manner that ensures minimal disruption to traffic, neighbouring sites and the environment.

Procedures

Requestor

  • Contractor shall apply for dewatering NOC by filling and signing Form ZADC # 21 .
  • Submit request at Customer Service Counter .
  • Contractor shall apply for dewatering NOC; the applicant shall specify the number of days, the number of deepwells and/or number of well points. In case the contractor exceeds the specified days re-submission of the same is to be obtained.

Documents Required

  • Copy of dewatering contractor professional license.
  • Key plan showing discharge pipe routing & discharge point (2 copies, A3 size)
  • NOC’s from relevant local authorities.
  • Outline program of work
  • Copy of fee receipt (as per fee matrix)

Customer Service Counter

  • All Submittal packages should be submitted at the Customer Service Counter by no later than 3:00 PM Sunday-Thursday. Any submission later than 3:00 PM will be registered for the following working day.

Zoning division-Development Control Department

  • Zoning division-Development Control Department reviews and process request.

Review Duration/Follow-up

  • 5 working days (excluding the submitted day)

Fees
As per fee matrix